Building Permit Application

Requirements Checklist

Document Copies Original? Where to Get
Any government-issued ID
1 Yes Applicant
Available at the counter
1 Yes LGU Office

Step-by-Step Procedure

Step Activity Responsible Duration
1 Submit application & requirements Receiving Officer 5 minutes
2 Verify / assess submitted documents Evaluator 15 minutes
3 Process & encode in the system Processing Officer 10 minutes
4 Approval / Signature of Head Department Head 1 day
5 Release of Document / Certificate Releasing Officer 5 minutes

Citizen Feedback

No feedback has been submitted yet for this service.

Quick Info

Office
Type Complex
Classification Government to Citizen
Processing 15 working days
ARTA Max 7 working days
Fees ₱2000.00
Schedule Monday – Friday, 8:00 AM – 5:00 PM

ARTA Compliance

Exceeds ARTA Limit

Processing time of 15 days exceeds the 7-day ARTA limit for complex transactions.