Water System Level III - Poblacion I
Project Progress
Behind schedule. Original target: Sep 3, 2026.
Start Date
Oct 23, 2025
Target
Sep 03, 2026
Actual
In Progress
Project Description
Installation of Level III water supply system.
Project Details
| Status | Ongoing |
| Category | Infrastructure |
| Barangay | POBLACION I |
| Project Manager | Engr. Juan Santos |
Budget Information
| Budget | ₱8000000.00 |
| Actual Cost | ₱5600000.00 |
| Funding Source | LGU Budget |
Utilization: 70%